Unit/Department Approval

Each unit/department has its own procedure for internal routing, fiscal review, and Dean/Director approval. Some units provide proposal coordinators for their faculty. In some units, the business office provides support for proposal preparation.

All proposals must be finalized and completed before OSP review. Proposals must be:

  • Reviewed by the business office or fiscal officer responsible for proposal
  • Entered into Banner
  • Signed by PIs, all Co-Is, and the Dean or Director for all departments involved in the project (UAF Proposal Routing Form)
  • Approved by all MAUs involved in the project
  • Completed (all e-forms and paper forms filled out; letters and documentation included with proposal)

 

Office of Sponsored Programs Approval

All proposals for external research and programmatic funding require administrative review by the Office of Sponsored Programs (suite 212 West Ridge Research Building) BEFORE submission to a sponsor. The OSP reviews proposals in the order in which they are received. Five business days is required for review and approval. If a proposal must be reviewed and returned to its department for mailing in less than five days, contact the OSP as soon as possible. The OSP will try to accommodate your "RUSH," but be cognizant of the fact that OSP staff are also reviewing proposals brought in on schedule by other investigators or departments. Proposals that involve cost sharing/matching, reduced F&A, or subawards REQUIRE MORE REVIEW TIME.

 

Authorized Organizational Representative

The OSP Director is the organizational representative delegated by the Chancellor to authorize proposal submissions after the proposal has been reviewed by the OSP. Do not submit a proposal to a sponsor without OSP authorization. The university has no obligation to accept awards that result from unauthorized proposals.

 

Paper Submissions

The OSP does not mail paper copies of proposals to the funding agency. After the OSP Director has signed a proposal, the OSP returns the proposal to its department. The department makes copies and submits the proposal to the sponsor. A copy of the proposal will be kept on file in the OSP. When the proposal is awarded by the agency, the proposal will be forwarded to Grant & Contract Services for account set up.

 

Electronic Submissions

As a result of the Paperwork Reduction Act more and more federal agencies are moving towards electronic proposal submission systems. The OSP is responsible for most electronic submissions. Some private sponsors accept electronic submissions as well. If your proposal must be submitted electronically, indicate that electronic submission is required on the UAF Proposal Routing Form.

 

Pre-Proposals, Notices of Intent (NOI), Letters of Intent (LOI), White Papers

The OSP only reviews contractually binding pre-proposals, notices of intent, letters of intent, or white papers that require AOR approval before submission to the sponsor. If the pre-proposal is non-binding and does not require AOR approval, then it does not need to be submitted to the OSP for approval before submission. If pre-proposal needs to be submitted electronically via NSF Fastlane or NSPIRES, please contact the OSP.

 

What else does the OSP review?

  • Supplemental Funding Requests: Requests for additional funding to add or supplement the current project (Note: You must use the most current F&A rate for supplemental requests.)
  • Annual Continuations: Requests for the next year's funding (only when required by the sponsor)
  • Renewals: Requests to “renew” the sponsor’s support for the project’s continuation
  • Pre-Award Revisions: Any changes to the proposal or budget before the official award is accepted by the university

 

What does the OGCA review?

  • Award documents
  • Annual progress reports
  • Amendments or modifications to existing awards
  • Post-award revisions to the proposal and/or proposal budget

 

RED STAMP

The OSP will return the original proposal to the department after approval if there are no outstanding compliance issues or missing documentation. This includes outstanding IRB, IACUC, and other protocols, IP issues, missing signatures, forms, or other needed paperwork. Original proposals that are returned to the department will have a RED STAMP (signature line) that has been signed by the OSP Director. Departments can send the original proposal with the signed RED STAMP directly to OGCA for award set-up. If the original proposal has not been returned to the department by the OSP, then OGCA must contact OSP before award set-up for more information about the proposal.

        All photos by Todd Paris.

Contact:

UAF Office of Sponsored Programs

West Ridge Research BLDG Suite 212
902 Koyukuk Drive

P.O. Box 757270
Fairbanks, AK 99775-7270

Phone: 907.474.6000
Fax: 907.474.5444

email: fyosp@uaf.edu

OSP Staff Directory