Project update

August 1, 2017

Work completed in July 2017

The construction is 48% complete. There were no major issues encountered during July. The following items were completed or are in progress:

Area Items installed Image
Baghouse Area
  • HVAC equipment (95%)
Boiler Area
  • Water wall welding (75%)
  • Ductwork (99%)
  • Steam piping (60%)
  • Interior concrete floors (100%)
  • Siding (70%)
  • Elevator (30%)
  • Electrical cable tray (40%)
  • HVAC equipment (50%)
Duct bank
Duct bank

Spaghetti
Boiler saturation tubing
Turbine Area
  • Cooling water piping (100%)
  • Steam piping (60%)
  • Control room and DCS room architectural (80%)
  • Cable tray (70%)
  • Turbine exhaust duct (70%)
Ash Handling Building
  • Install stairs and railings (100%)
Material Handling Building
  • Foundation (100%)
MH foundation
Material handling foundation
Air Cooled Condenser (ACC)
  • Steel erection (100%)
  • Fans, exhaust duct and tubes (10%)

Anticipated work for August 2017

The following items are scheduled for installation in August 2017:

Area Items scheduled for installation Image
Baghouse Area
  • Install compressed air header
  • Complete piping
Boiler Area
  • Water wall welding
  • Place interior concrete slabs
  • Roofing
  • Blowdown and drain
  • Electrical cable tray
  • Progress towards the major milestone of boiler hydrostatic test
Turbine Area
  • Complete steam and cooling piping
  • Electrical cable tray
  • Install control cabinets
Ash Handling Building
  • Install siding piping and electrical
Material Handling Building
  • Erect structural steel
ACC
  • Install fans, turbine exhaust duct and coils

AN ENERGY SOLUTION

Back to Top