Project update

February 23, 2016

  • Construction for Work Package No. 1 was completed in September, 2015 and was under budget.
  • Equipment Procurement activities in Work Package No. 1 are continuring.  Purchase Orders were issued for the following equipment:
    • Material Handling System
    • Ash Handling System
    • Boiler Feed Pumps
    • Feedwater Heater
    • Deaerator Tank
    • Exhaust Stack
    • Auxiliary Cooling system
    • Vertical Turbine pumps
  • Procurement is in progress for electrical equipment and distributed control system
  • Work Package No. 2 was issued on January 29, 2016 for $31,791,000.
  • The scope of work for Work Package No. 2 consists of the following:
    • Project General Conditions through 2017
    • Boiler and turbine building foundations
    • Turbine building steel
    • Exterior enclosure for boiler and turbine buildings
    • Final site grading
    • Railroad track replacement
    • Pipe bridge
  • Ground thawing is in progress and foundation construction will begin on February 29, 2016.
  • The general sequence of work for summer/fall 2016 is:
    • Structural mat for boiler basement (5' thick)
    • Basement walls
    • Basement steel and first floor
    • Turbine and baghouse slabs (4' thick)
    • Boiler building structural steel
    • Start boiler erection simultaneously with steel erection
    • Building envelope
  • Construction activities will continue through the winter of 2016-2017
  • Major equipment deliveries are in Fall 2016 through Spring 2017

AN ENERGY SOLUTION

Back to Top