Project update

July 1, 2017

Work completed in June 2017

The construction is 49% complete. There were no major issues encountered during June. The following items were completed or are in progress:

Area Items installed Image
Baghouse Area
  • HVAC equipment (75%)
Boiler Area
  • Generation bank tube installation (100%)
  • Water wall welding (35%)
  • Ductwork (99%)
  • Steam piping (45%)
  • Interior concrete floors (75%)
  • Siding (70%)
  • Elevator (30%)
  • Electrical cable tray (15%)
  • Erect exhaust stack (100%)
Stack erection
Stack erection
Turbine Area
  • Cooling water piping (95%)
  • Steam piping (5%)
  • Control room and DCS room architectural (70%)
  • Cable tray (30%)
  • Turbine exhaust duckt (70%)
Ash Handling Building
  • Install stairs and railings (100%)
Material Handling Building
  • Foundation (70%)
Material handling progress
Material handling progress
Air Cooled Condenser (ACC)
  • Place foundation (100%)
  • Steel erection (85%)
ACC progress
ACC progress

Anticipated work for July 2017

The following items are scheduled for installation in July 2017:

Area Items scheduled for installation Image
Baghouse Area
  • Install compressed air header
  • Complete piping
Boiler Area
  • Water wall welding
  • Place interior concrete slabs
  • Roofing
  • Blowdown and drain
  • Electrical cable tray
  • Progress towards the major milestone of boiler hydrostatic test
Turbine Area
  • Complete steam and cooling piping
  • Electrical cable tray
  • Install control cabinets
Ash Handling Building
  • Complete structural steel
  • Install ash handling equipment
  • Install siding
Material Handling Building
  • Place foundation (there are seven different foundation elements)
ACC
  • Install fans, turbine exhaust duct and coils

AN ENERGY SOLUTION

Back to Top