Project update

January 1, 2018

Work completed in October through December 2017

Construction is 76% complete.  Major items completed since the last update are:

Major items completed since the last update are: Image
  • Material handling siding (100%)
  • Piping – all systems (80%)
  • Electrical cable tray (100%)
  • Electrical cable installation (65%)
  • Air Cooled Condenser (100%)
  • Control System (20%)
  • Boiler refractory (100%)
  • Boiler casing (100%)
  • Boiler Insulation (50%)
  • Steam pipe cleaning – Steam blow (70%)
  • Turbine oil flush (100%)
Completed boiler piping
Completed boiler piping

Completed steam blowout
Completed steam blowout

Items in progress: Image
  • Piping – all systems
  • Electrical cable installation
  • Electrical distribution equipment
  • Variable frequency drives
  • Instrumentation
  • Control system
  • Atkinson control system modifications
  • Boiler insulation
  • Pipe insulation
  • Ash Handling equipment and HVAC
  • Material handling equipment and HVAC
Electrical equipment
Electrical equipment

AN ENERGY SOLUTION

Back to Top