Project update

July 7, 2015

  • The project was rescoped during the period of February 2015 to April 2015 to fit within available funding. The primary scope changes were:
    • Changing from two 140,000 lb/hr boilers to one 240,000 lb/hr boiler
    • Deleting the administration wing
    • Deleting the parts storage warehouse
    • Deferring utilidor construction
    • Relocating the coal unloading facility to the north side of the facility
  • A new boiler contract was signed on June 2, 2015, with Babcock & Wilcox Power Generation Group for $30,807,873.
  • A new steam turbine contract was signed on June 21, 2015, with Shin Nippon Machinery for $6,707,260. The new extraction steam turbine is sized at 17MW.
  • Construction Work Package No. 1 was signed on June 24, 2015, with Haskell/Davis JV for $44,172,298. The Work Package No. 1 scope consists of:
    • Site excavation and backfill
    • Deep vibratory compaction
    • Parking lot construction
    • Equipment procurement including material handling system, ash handling system, exhaust stack, pumps, valves and electrical equipment
  • Site construction activities started on July 6, 2015

AN ENERGY SOLUTION

Back to Top